Rahughat Hydropower Project

MYAGDI: Nepal’s 40-megawatt Rahughat Hydropower Project has officially entered commercial production, ending a construction journey that lasted approximately 15 years.

Developed by Raghu Ganga Hydropower Limited, a subsidiary of the state-owned Nepal Electricity Authority (NEA), the project is located in Raghuganga Rural Municipality of Myagdi district.

According to project Managing Director Ganesh KC, the project has completed its testing period and commenced commercial electricity generation.

The testing process, which began on October 6, was extended after flooding in the Kali Gandaki River damaged the powerhouse premises at Tilkechaur on October 11.

Project faced repeated delays

Construction of the Rahughat Hydropower Project began in 2010 under an initial plan to generate 32 megawatts of electricity.

The NEA initially awarded a civil construction contract worth approximately Rs. 2.5 billion to India’s IVRCL. However, the contract was cancelled in 2015 after the contractor faced financial difficulties, with physical progress reaching only around 12 percent over five years.

The project was subsequently restructured, increasing its installed capacity from 32 MW to 40 MW. Raghu Ganga Hydropower Limited was established as an NEA subsidiary to take the project forward.

The construction process faced further challenges, including contractor-related problems, the COVID-19 pandemic, floods, landslides, customs clearance difficulties and shortages of riverbed construction materials.

A new civil construction contract worth approximately Rs. 6 billion was awarded to India’s Jaiprakash Associates in 2017.

Expected to generate around 240.59 million units annually

The project includes a 6.27-kilometre main tunnel, a dam system and two water storage ponds. Its powerhouse is located at Tilkechaur in Raghuganga Rural Municipality.

The electricity generated by the project is connected to the national transmission system through the 220-kV Dana-Kushma transmission line.

Under its power purchase agreement with the NEA, the project is expected to generate approximately 240.59 million units of electricity annually.

The project was financed through investments from the Government of Nepal and the NEA, alongside a concessional loan of approximately US$67 million secured through India’s EXIM Bank.

Boost to Nepal’s hydropower sector

The commencement of commercial production marks an important milestone for Nepal’s energy sector, adding 40 MW of electricity generation capacity to the national grid.

The project is also expected to contribute to electricity availability during the dry season and support the country’s growing energy demand.

According to Myagdi Chamber of Commerce and Industry President Subin Shrestha, the Rahughat project has played an important role in encouraging hydropower development in the district. Around 10 other hydropower projects have subsequently been completed in Myagdi.

The project’s commercial operation brings an end to one of the district’s longest-running infrastructure development projects and highlights both the opportunities and challenges associated with hydropower construction in Nepal.