RASUWA: Syabrubesi in Rasuwa district remains disconnected from Nepal’s national road network three months after the Bhotekoshi flood swept away key infrastructure on August 26.
The lack of a road link has disrupted daily life in parts of Gosainkunda and Aamachhodingmo rural municipalities. Residents in upper areas are facing difficulties accessing healthcare, transporting food supplies and moving between settlements.
Local representatives say people needing urgent medical attention have been forced to rely on helicopters, while temporary wooden footbridges are being used to cross some sections.
The flood also devastated the Rasuwagadhi border crossing, bringing cross-border trade to a halt.
Authorities are preparing to install a 76-metre Bailey bridge over the Bhotekoshi River near Syabrubesi. The bridge is expected to restore road access to the area, with installation targeted for the final week of Mangsir.
Officials have also set a mid-January target for opening a basic temporary road track towards the Rasuwagadhi border, allowing limited vehicle movement.
The National Planning Commission has estimated that the floods caused Rs 174 billion in infrastructure losses, while Rs 382.83 billion would be required for recovery.