KATHMANDU: Kathmandu Metropolitan City (KMC) has started construction of a dedicated school and research centre for children with autism in Anamnagar, Ward No. 29, in a move aimed at expanding access to specialised education, training and support services.

Acting Mayor Sunita Dangol laid the foundation stone of the Kathmandu School for Children with Autism and Research Centre on Wednesday, November 25, in the presence of Ward Chairperson Kush Kumar Dhakal, local representatives, parents and residents.

Speaking at the foundation ceremony, Dangol emphasised that every child deserves equal access to education, opportunities and a dignified life, regardless of disability.

She said the education system must be equipped to address the different learning, communication and behavioural needs of children with autism and intellectual disabilities.

According to Dangol, the project is intended to create a more inclusive urban environment where disability does not become a barrier to education and other fundamental rights.

Five-Storey Building Planned

The new facility will be constructed on a 450.80-square-metre plot located east of the Ward No. 29 administrative building.

Designed by Kathmandu Metropolitan City’s Department of Public Works, the five-storey structure will have a total floor area of approximately 18,500 square feet, including a 3,500-square-foot basement.

The building will include training and learning facilities on the first three floors, while the fourth floor will accommodate administrative and research offices. The fifth floor will feature an open terrace.

The ground floor will include an open recreational space for children, a main entrance, stairs and an elevator. The basement will provide parking facilities for up to 30 two-wheelers.

The building will also feature an eight-person-capacity elevator, accessible rooms and disability-friendly toilet facilities.

Construction Contract Worth Rs. 97.74 Million

The estimated construction cost of the project was initially set at Rs. 109.18 million. Following the public procurement process, the construction contract was awarded for Rs. 97,745,626.

The construction work order was issued to the contractor on November 19, 2026. According to the agreement, the building is scheduled to be completed by mid-April 2028.

Centre to Support Children and Families

Beyond providing specialised educational facilities, the centre is expected to serve as a hub for skill development, training, research and support for parents of children with autism.

KMC Ward 29 Chairperson Kush Kumar Dhakal said the facility would help improve the skills and knowledge of children while also providing opportunities for training and research.

Parents and organisations working in the field of autism have welcomed the initiative, highlighting the need for accessible specialised services.

The project is expected to help address the challenges faced by families who currently depend on private institutions for specialised education and support, which can involve substantial monthly expenses.

Step Towards Inclusive Education in Kathmandu

The establishment of the autism school and research centre marks an important step towards strengthening inclusive education and disability support services in Kathmandu.

Once completed, the facility is expected to provide a dedicated environment where children with autism can access education, develop practical skills and receive support suited to their individual learning needs.

The initiative also highlights the growing role of local governments in expanding educational opportunities and creating more inclusive public infrastructure.