Vehicular movement along the Narayangadh-Mugling road section will be restricted for five hours daily from December 29 as authorities resume landslide prevention work at Tuinkhola.
The District Administration Office, Chitwan, has announced that the road will remain closed to all vehicles from 11 am to 4 pm every day until further notice.
Assistant Chief District Officer Ishwori Prasad Sharma said the restriction was necessary to ensure safety during the ongoing slope stabilisation work, which involves potential risks from falling rocks and other hazards.
The Road Division Office, Bharatpur, has been working to address recurring landslides in Tuinkhola by introducing specialised engineering measures aimed at ensuring long-term road safety. Various preventive measures have been undertaken since last year to minimise road disruptions during the monsoon and winter seasons.
The upcoming work will include slope stabilisation through the ‘nailing’ technique, which involves removing large rocks and inserting steel rods into the hillside to strengthen unstable sections. Horizontal drainage systems and bioengineering methods will also be used to control water flowing from the slopes.
Amit Kumar Sharma, chief engineer at the Road Division Office, Bharatpur, said bioengineering measures would be applied in both two-dimensional and three-dimensional forms, depending on the condition of the terrain. Nailing technology will primarily be used to reinforce vulnerable slopes.
The prevention work, which was suspended last Ashoj, is now being resumed. Sharma said the project had previously continued even when the Prithvi Highway was closed at Krishna Bhir. However, work at Tuinkhola was temporarily stopped to prioritise reopening the Krishna Bhir section.
Based on the current condition of the road, the project may require at least 15 days of restricted movement, Sharma said. The final duration will be determined after a technical assessment, while the daily closure schedule will remain in effect until further notice.
Meanwhile, landslide prevention work at Ghoptebhir, near Mugling along the Prithvi Highway, is expected to be completed by tomorrow. The highway is likely to reopen the following day, after which work at Tuinkhola will resume.
The administration has clarified that the Prithvi Highway connecting Kathmandu and Pokhara through Mugling and Aanbukhaireni will remain operational.
The District Administration Office has apologised for the inconvenience caused by the restrictions and urged passengers and motorists to plan their journeys accordingly.